Cajamarquilla Mining Unit
--- Quality Control and Management ---
Construction consultancy for the 5th heightening of the DLN
- Fecha: -
- - 2021
- Cliente: NEXA Resources
- Coordenadas: 24H7+JMQ, Lurigancho-Chosica 15461
- Resumen: The project focused on providing specialized construction advice through weekly technical visits and monthly coordination meetings. The main objective was to guarantee the quality of the work and ensure compliance with technical standards. Thorough inspections were conducted, laboratory results were reviewed, and recommendations were provided to improve the construction process. In addition, constant communication was maintained with the construction team through detailed meetings and reports.
-
Descripción:
- Ongoing advice was provided by a civil engineer, focused on optimizing the construction process and taking advantage of resources in the protection works of the WWTP and PS2.
- Technical queries related to the construction of the WWTP protection dam at the 4,214 m above sea level were attended to.
- Designs were developed for the WWTP protection dam, the protection works of PS2 and the access road to the PS1 pool.
- Five plans were executed for the extension of the R4 and R5 dams, based on specifications and manuals.
- Material measurements, a schedule and a detailed execution plan were prepared for the designed works.