Colquijirca Mining Unit
--- Quality Control and Management ---
Quality assurance for the construction of the regrowth of the R4-R5 dikes and QA of production of construction materials for the R4-R5 dikes.
- Fecha: 2022
- - 2023
- Cliente: Sociedad Minera El Brocal S.A.A
- Coordenadas: 6PQP+RWQ, Colquijirca 19400
- Resumen: A rigorous quality assurance process was carried out in the construction of the R4 and R5 dams, complying with the highest standards and technical specifications. Through meticulous management and the application of best practices, we ensured the robustness and durability of the work. From the initial design phase to the completion of construction, we optimized resources and minimized risks, delivering a project of exceptional quality that exceeded the client's expectations.
-
Descripción:
1. QA supervision of the heightening of the R4 and R5 dams.
2. QA laboratory for the heightening of the R4 and R5 dams.
3. QA supervision of the production of materials in the quarry for the heightening of the R4 and R5 dams.
4. QA laboratory for the production of materials for the heightening of the R4 and R5 dams.
5. RFI response.
6. Quality dossier.
7. External laboratory tests.